CSS Fencing completed - Jan 2024
B-Block 1st and 2nd floor 2n coat painting WIP - Jan 2024
A-Block GF to 3rd floor door frame fixing completed rest WIP - Jan 2024
Club house fins WIP - Jan 2024
Kids play area equipment's fixing completed - Jan 2024
C-Block common area painting WIP - Jan 2024
C-Block QA started - Jan 2024
A-Block Terrace tiling completed - Jan 2024
Terrace pergola completed - Jan 2024
Clubhouse swimming pool tiling completed - Jan 2024
Clubhouse swimming pool change room tiling completed - Jan 2024
Pool door fixing completed - Jan 2024
Ramp railing fixing WIP - Jan 2024
Lift lobby door fixing WIP - Jan 2024
Ramp granite laying completed - Jan 2024
All blocks gail connection completed - Jan 2024
S^ side creepers plants support WIP - Jan 2024
External plantation WIP - Jan 2024
Lift lobby Z-louvers installation completed - Jan 2024
WTP equipment's installation WIP - Jan 2024
B and C block CP fittings installation WIP - Jan 2024
Clubhouse basement painting WIP - Jan 2024
Basement DB installation completed - Jan 2024
C-Block Solar water heater installing WIP - Jan 2024