Block B: South side view - Oct 2023
Block C: South side view - Oct 2023
Block D: South side view - Oct 2023
South side podium water proofing completed - Oct 2023
Block A: 1st floor to 4th floor flats tiling completed - Oct 2023
Swimming pool tensile fabric installation completed - Oct 2023
N^side podium waterproofing WIP - Oct 2023
Block A: staircase tiling completed - Oct 2023
Block A: Lift cladding WIP - Oct 2023
Clubhouse glazing work WIP - Oct 2023
Block D: lift car inside granite laying completed - Oct 2023
Planter box texture work WIP - Oct 2023
Compound wall concertina WIP - Oct 2023
Basement VDF WIP - Oct 2023
Exit and entry ramp roof covering WIP - Oct 2023
N^ side compound wall texture WIP - Oct 2023
W^ side compound wall texture WIP - Oct 2023
Planter box coping WIP - Oct 2023
N^ side light pole installation WIP - Oct 2023
OWC outside texture completed - Oct 2023
S^ side compound wall painting WIP - Oct 2023
D & C lift cladding completed - Oct 2023
STP electromechanical ducting WIP - Oct 2023
Block D: Solar water heater installation completed - Oct 2023
A & B basement piping WIP - Oct 2023
All blocks shaft branch piping work completed - Oct 2023
Block D: 4th floor CP and sanitary fixing WIP - Oct 2023
DG low side WIP - Oct 2023
Basement cable tray works in progress - Oct 2023
Brigade Gem Tower A: Milestone Release – On Commencement of Painting - Oct 2023
Brigade Gem Tower A: Milestone Release – On Commencement of Painting - Oct 2023